EXERGY 25MW MEHMETAN GEOTHERMAL PLANT SUCCESSFULLY COMPLETED THE PERFORMANCE TEST

Another great success for Exergy at the beginning of 2017.

The 25 MW geothermal plant Mehmet Han, successfully completed its performance test, with an over performance rate of about 2.5 MW.

The geothermal plant is located in the south west of Turkey and is one of the two units supplied by Exergy to Kipas Holding.

The plant is equipped with 3 Radial Outflow turbines for the two pressure levels; two 9.5 MW turbines each for the High Pressure level and one 6MW turbine for the low pressure level.

The over performance rate will give the client an overall major income due to the increased total power output.